Saturday March 7th, 2020 8:48am, with a spring rainstorm blowing in to the the San Francisco Bay area Saturday morning, we experienced another transmission level voltage sag affecting customers throughout the region. Transmission line voltage sagged to less than 81% of normal for 4.5 cycles, or about 1/10th of a second for the City of Santa Clara’s grid.
Customers reported impact from this widespread voltage sag on their power quality sensitive loads and equipment. No root cause has yet been identified.
APT provides solutions to harden your facility against utility failures like this before they happen and capture the power quality data – so you can verify your return on your investment by reducing or avoiding impacts.
If this information is useful, please subscribe to APT’s power quality blog to be notified when this happens in the future.